THREE BRUSH GENERATOR OPERATION:
The three brush generator design
required removing the cover and adjusting the position of the third brush in
order to change the charging rate. By moving the position of the third
brush the voltage applied to the field windings was changed. This in turn
changed the strength of the magnetic field applied to the rotating armature and
thus set (or limited) the maximum charging rate, or current output, of the
generator. The generator would continue to charge at this fixed current rate
all the time, regardless if the battery was boiling over or dead, lights on
or off, it didn’t matter. This was fine if the electrical load on the system
remained constant, but motorcycle loads usually do not. If the battery was low,
or additional loads such as lights were turned on, the generator output remained
the same. In short, the 3 brush generator cannot automatically compensate
for any type of varying electrical loads.
The 3 brush generator did not have
any type of voltage regulator built into it. Adjusting the 3rd brush
only changed the current output of the generator. The battery essentially became
the voltage regulator in the system. As a result, the generator consistently
applied an excessively high voltage to the battery (on the order of 8 – 8.5
volts). In fact, as the battery reached a fully charged state, the generator
current output actually increased slightly as did the battery voltage! Over
prolonged periods, this would cause overcharging of the battery. Many batteries
and fine paint jobs have suffered from this poor regulating system!
If for some reason the battery were
to be dropped out of the circuit, the generator output voltage would now be
unregulated. If allowed to run unregulated, the generator voltage would quickly
rise and could easily get up to 40 or 50 volts. This would in turn burn out the
light bulbs and other electrical equipment, such as ignition coils. Excessive
heat would be generated internally and quickly damaged the generator as well.
TWO STAGE, THREE BRUSH GENERATOR
OPERATION:
In an effort to eliminate over and
under charging problems, both Harley Davidson and Indian adopted their own
version of a two charge system. Both systems still used a 3 brush generator but
provided a high output as well as a low output setting. Moving the 3rd
brush would change both settings simultaneously, proportionately limiting the
maximum current output of each setting.
Harley Davidson models were
equipped with the model 32 E generator starting in 1932. This remained standard
equipment through 1954. Operation consisted of energizing only one smaller field
winding during engine operation only. This provided enough current output from
the generator to run the ignition system and place a small constant charge into
the battery. When the lights were turned on, the second larger field winding was
energized, resulting in a much higher output. This high output could run the
lights and ignition as well as a small charge into the battery. Properly
adjusted, the Harley system was simple, reliable and effective, as long as
standard lighting equipment was retained.
Starting in 1938 as an option,
Indian Chief, Scout and 4 cylinder models could be equipped with the TC
regulator and a model GDE high output generator. This system became standard
equipment in 1948- 1953. However, the verticals were never equipped with this
system. Operation consisted of energizing both field coils simultaneously.
During low battery voltage conditions, all of the voltage provided by the 3rd
brush was applied directly to the field windings, resulting in a high charge
rate. When battery voltage rose above a set point, a relay inside the regulator
would switch and insert a large carbon resistor into the field circuit. This
dropped the field voltage considerably which resulted in a much lower generator
output. In theory, if adjusted properly, these 2 charge rates would match the
electrical demands when running with lights on, or off. This system worked well
but only with standard lighting equipment and when adjusted properly. However,
it did require routine maintenance and very careful adjustment of the relay
points and spring tension within the TC regulator. The large carbon resistors
could break or overheat and burn out, which would result in a constant high
charge rate.
CUTOUT RELAY OPERATION:
The cutout relay, or reverse current
relay, is a switch located in line between the generator and the battery.
The purpose of this relay is to prevent battery discharge through the generator
whenever the engine is shut off. If this relay were not in the circuit, the
battery would energize the generator and attempt to turn the generator like a DC
motor. This would quickly result in a dead battery and a very hot or possibly
damaged generator!
Some early cutout switches were
centrifugally operated. Most cutouts however are electro-mechanical relay
switches. Regardless of the design, both types required periodic maintenance and
adjustment. Over time they became prone to sticking closed at times. This would
of course drain the battery in a very short time.